Single sign-on (SSO) is a way to securely authenticate with multiple websites and apps by logging in only once. In Ganttic there are 3 SSO options to choose from: OneLogin, MS Azure, and Google. OneLogin and Microsoft Azure help you to create secure smart identities for all Ganttic Users within your organization. It uses the SAML 2.0 protocol which is utilized by web browsers to enable SSO through secure tokens. Using standard cryptography and digital signatures to pass a secure sign-in token from an identity provider to a SaaS application (like Ganttic). And with plenty of benefits for your project management.
Must-know about this feature
With OneLogin you can sign in with just a click using your organization's Ganttic subdomain (organization.ganttic.com). No passwords needed, simple and secure! This feature is available for PRO accounts only and is optional. In order to use it you have to create your organization's unique Ganttic subdomain, sign up for a OneLogin account and link it with Ganttic according to the instructions below. Google and Microsoft's Azure SSO doesn't require any previous configuration and is available with all Ganttic plans (free one included).
Set up OneLogin SSO
Create Account Subdomain
Find instructions here. Subdomains are necessary to link OneLogin (SAML 2.0) and other Single Sign-On (SSO) options with Ganttic but you can also use this for the sake of customization alone and continue using the subdomain with regular username and password option. Using subdomains is optional if you don't want to use the SSO options.
In OneLogin, go to "Applications" and select Ganttic from the list
This will open additional configuration options for Ganttic.
Click on "SSO"
You can find it on the left menu.
Click on "View Details" in the "X.509 Certificate" section
This will reveal the certificate in full.
Click on "Copy to Clipboard"
You can find it on the right hand side.
Go back to Ganttic > Settings > SSO and paste the certificate to the corresponding section
Return to OneLogin > Applications > Ganttic > SSO and copy "SAML2.0 Endpoint (HTTP)"
Paste the URL into corresponding section in Ganttic > Settings > SSO
Return to OneLogin > Applications > Ganttic > SSO and copy "Issuer URL"
Paste the URL into corresponding section in Ganttic > Settings > SSO
Click on "Save" below.
Click "OK" to confirm
Each time you go to the subdomain to sign in you will see the OneLogin SSO option
Click on it to enter Ganttic Planner.
You have to be signed in to OneLogin. If you aren't then you will be prompted to do so on the go.
Sign in With Google
Click on "Sign in with Google" icon
Enter your email and password to sign in.
Make sure to use the same email address as with your Ganttic account and that you are already signed in to your Google Account (in another browser tab).
Sign in with Microsoft's Azure AD
Click on "Sign in with Microsoft"
Enter your Ganttic email and Azure password to sign in.
Make sure to use the same email address as with your Ganttic account and that you are already signed in to Azure (in another browser tab). In Azure app panel make sure Ganttic is in the list of allowed apps.